PROJECT OVERVIEW

Categories:
Client: Korone Engineers CC
Location: South Africa
Completed: November 2017
Value: R8,000,000.00
Engineer: Hi-Tech Consulting

PROJECT OVERVIEW

Korone Engineers cc: Ventersdorp Waste Water Treatment Plant (WWTW) Optimazation

The firm was appointed by Korone Engineers cc to undertake optimization of Ventersdorp WWTW to improve operations and effluent quality. The optimization aimed at establishing the current condition of the plant by evaluating all major unit processes, assessing the plant’s performance, identifying performance limiting factors and developing proposed interventions. Proposed interventions included construction of 2 bio-digestors and a sludge drying bed to deal with excess sludge in the system.